摘要
秦岭终南山公路隧道是中国目前在建的最长的公路隧道。对于这样的特长公路隧道 ,其通风方案的优劣不仅关系到隧道的建设规模和将来的运营成本 ,而且和隧道的防火救灾相关。详细讨论了秦岭终南山公路隧道通风技术中的几个关键问题 ,并初步探讨了几种可能通风方案的优缺点 。
The Zhongnanshan highway tunnel in Qinling is the longest tunnel under construction in China now. For this extra long tunnel, the good and the bad of its ventilation scheme not only affect the construction scale and the operating cost, but also connect with the fire prevention and fire fighting. The several key problems of the ventilation technique and the strong and weak points of five posible ventilation scheme are discussed. Moreover, the corresponding problems for further research are presented.
出处
《长安大学学报(自然科学版)》
EI
CAS
CSCD
北大核心
2002年第5期48-50,共3页
Journal of Chang’an University(Natural Science Edition)
关键词
通风方案
公路隧道
通风技术
Zhongnanshan mountain in Qinling
highway tunnel
ventilation
technique