摘要
主要介绍了国电常州电厂一期工程(2×600MW)机组循泵房沉井施工方案的选择和施工工艺,不局限于设计采用不排水下沉,而是经过论证,采用排水下沉而后最终干封底成功的实践,大大缩短了工期,降低了成本。
The author describes the State Power Changzhou Power Plant 1st Phase engineering(2 × 600MW) circulating room caisson construction scheme selection and construction process.It is not limited to the design using non-water sink,but after a demonstration,the use of sink drain and then the final successful practice of dry back shortens the construction period and reduces costs.