摘要
自动化仪表安装工程,是冶金建设工程中比较靠后的工序,仪表安装工程的施工进度对整个工程的工期有着很大的影响。为了保证工程进度,根据施工的具体实例,从施工的人员因素、机具因素、施工材料因素、施工方法因素、施工环境因素5方面,对影响施工进度的各环节进行分析,找出影响工程进度的原因,并提出具体的解决办法,达到保证工程进度的目的。
Automation instrument installation engineering is the later process for metallurgical construction engineering.The construction process of instrument installation engineering has great effect on the total period.In order to assure engineering process,and according to special examples,from people factors,instrument factors,construction material factors,construction method factors and environment factors,every part affecting construction process is analyzed,and corresponding solving methods are put forward to assure construction period.
出处
《施工技术》
CAS
北大核心
2011年第S1期443-446,共4页
Construction Technology
关键词
自动化仪表
仪表施工
进度管理
automation instrument
instrument construction
process management