混凝土排水管道退管施工工艺 被引量:8

Withdrawing Pipe-jacking Construction Technology of Concrete Drainage Pipe
下载PDF
导出
摘要 顶管工程在施工过程中不可避免的会遇到障碍物,以上海某顶管工程在穿越公路段时遇到不明地下障碍物为例,在无法清障的条件下,采用了新的退管技术实现了成功退管。详细阐述了退管工艺流程,以及施工中的关键技术和防护措施。最终重新设定了轴线进行顶管,从原工作井与接收井进出洞,节约了施工成本,解决了无法清障的难题,为顶管施工提供了一种可靠的退管施工工艺。 Pipe-jacking often encounter obstacles in the construction process,based on engineering practice in Shanghai,the pipe-jacking encountered unknown underground obstacles in crossing the highway,under the condition of can't remove obstacles,the adoption of new construction technique of pipe withdrawing to achieve a successful in the actual project. The construction technology of withdraw pipe and key technology and protective measures in construction were introduced in this paper. Reset the axis of the pipe jacking at last,original work well into the hole,the well received original hole,and save construction cost. A reliable construction way for pipe-jacking encountered obstacles was provided.
出处 《施工技术》 CAS 北大核心 2016年第S1期530-532,共3页 Construction Technology
关键词 顶管 地下障碍物 退管施工工艺 pipe-jacking underground obstacles construction technology of withdrawing pipe
  • 相关文献

参考文献2

  • 1GB 50268-2008.给水排水管道工程施工及验收规范[S]. 2008
  • 2CECS 246-2008.给水排水工程顶管技术规程[S]. 2008

共引文献9

同被引文献22

引证文献8

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部