摘要
阐明研究电网“零启动”方案的意义 ,重点介绍《湖北 2 2 0 k V及以下主网“零启动”方案》,并结合湖北电网首次“零启动”试验过程 ,提出下一步改进工作的建议。
The paper expounded the value of researching the power grid 'black start' plan, and focused on the 'black start plan in Hubei Power 220kV and below network'. In accordance with the testing of Hubei Power Grid first ' black start', the paper gave out suggestions for the next step improvement.
出处
《湖北电力》
2002年第4期88-90,99,共4页
Hubei Electric Power
关键词
湖北
电网
零启动
试验
电力系统
Hubei Power Grid
black start
plan and test
preliminary discussion