摘要 目前 ,还没有一种施工方法能有效地解决在非全风化并具有一定强度的岩层或砂卵石层中建造薄壁混凝土防渗墙难的问题。冲切成槽薄壁混凝土防渗墙施工技术是在原冲击成槽建造防渗墙的基础上 ,对冲击钻头和施工工艺加以改进 ,用扁钻头代替十字钻头 ,用正反两种循环系统进行泥浆循环的一种新防渗墙施工方法。实践证明 ,该工法为在风化岩层和砂卵石层中建造薄壁混凝土防渗墙提供了可能。 At present, no method is available for effectively solving the difficult problem of constructing thin concrete cutoff walls in non-completely weathered strata or sand/gravel deposit with a certain strength. The present technique is a new thin cutoff wall construction method by modifying the original method as to use flat drill bit instead of cross bit and adopt positive and negative circulating system. It is proofed by practice by this method it is possible to construct thin concrete cutoff walls in weathered strata and sand/gravel deposit.
出处 《西北水电》 2002年第3期25-27,共3页 Northwest Hydropower
关键词 混凝土 湖北 漳河水库 防渗治理 薄壁防渗墙 冲切成槽 泥浆循环 工程施工 thin cutoff wall impact cutting slurry circulation
  • 相关文献

参考文献3

  • 1湖北水电勘察设计研究院.湖北省漳河水库工程地质勘察报告[M].湖北:湖北水电勘察设计研究院,1985..
  • 2湖北水利科学研究所.湖北省漳河水库副坝薄壁塑性混凝土防渗墙试验设计方案[M].湖北:湖北水利科学研究所,1999..
  • 3湖北省水电工程二处.湖北省漳河水库副坝7+050~7+380、5+400~5+700段薄壁塑性混凝土防渗墙施工组织设计[M].湖北:湖北省水电工程二处,2000..