摘要
该文主要论述了冷藏库隔汽隔热层的施工 ,因工程特殊、质量要求高 ,所以本工程采取了周密的安排 ,从施工准备、施工工艺到该注意的几个问题都作了详尽的论述和说明 ,最终保证了工程的顺利完成 ,质量完全达到设计要求。
The construction of strata isolation air and heat in refrigeration storeroom is discussed. The project has it speciality and the demand of quality is high, so a careful plan was adopted. This essay made a detailed discussion and pointed out in construction preparedness and technology, the project was completed and fullfill the quality requirements in design.
出处
《土工基础》
2002年第3期44-45,共2页
Soil Engineering and Foundation
关键词
冷藏库
隔汽层
隔热层
搭接长度
工程施工
Stratum of isolation air
stratum of isolation heat,length of build link