抽水蓄能电厂削峰填谷作用已被电力行业所认可 ,但是对抽水蓄能电厂的调峰服务以发电量作为财务经营核算依据 ,对于其调峰作用未予经济补偿 ,阻碍了抽水蓄能电厂的投资回收和调峰的积极性。为此 ,以十三陵蓄能电厂投产 6年以来生产实际为参考 ,着重分析了抽水蓄能电厂调峰对机组和人员的影响等项目 ,并运用等额还贷方法深入分析了抽水蓄能电厂调峰服务补偿的必要性 。
The peaking and value filling functions of pumped storage power plant has been generally acknowledged by the power sector. Because pumped storage power plant only can calculates its energy output during peaking period but cannot get some economic compensation for its peaking function, it hinders the investment recovery and the peaking enthusiasm of pumped storage power plant. For this reason, taking the actual production of Shisanling Pumped storage Power Plant for six years since its operation into account, this paper analyzes with emphasis the affecting items of peaking service on generating unit and employees of pumped storage power plant and the compensation necessity of peaking service of pumped storage power plant. Then this paper puts forward the method of 'four step system' compensation.
出处
《水力发电》
北大核心
2002年第9期14-15,共2页
Water Power
关键词
十三陵蓄能电厂
调峰服务
补偿分析
电力市场
peak modulation service, compensation analysis, Shisanling Pumped storage Power Plant