摘要
介绍了锡盟—山东1000 kV特高压交流输电线路工程(包2段)测量中GPS测量、调绘、选定线测量、平断面测量、校核测量、定位测量、塔基断面与塔基地形测量等测量方法。
This paper expounds the engineering measurement methods of Ximeng-Shangdong 1000 kv extra high voltage DC transmission line(package 2),including GPS measurement, annotation,line selection,layout survey,flat cross section measurement,checkmeasurement,positioning measurement, kentucky section and topographic survey,and so forth.
出处
《电力勘测设计》
2017年第S1期72-78,共7页
Electric Power Survey & Design
关键词
GPS测量
调绘
选定线测量
平断面测量
校核测量
定位测量
塔基断面
塔基地形
GPS measurement
annotation
line selection
layout survey
flat cross section measurement
checkmeasure ment
positioning measurement
kentucky section and topographic survey