摘要
通过分析广州发电厂 2号锅炉乙磨煤机出口轴瓦损伤情况 ,采用不顶大罐 ,“灌油慢转打磨法”进行修复。修复后经过近 7年的运行 ,无异常情况 。
Through analysing the bearing pad damage of ball tube mill No.2 belonging to boiler No.2 at Guangzhou Power Plant, a new repair method, namely oil-pouring low speed grinding method without lifting the big canister, was selected. After repairing, there was no abnormality occurred in long-term operation of about seven years, it is clear that the new repair method being simple and correct.
出处
《热力发电》
CAS
北大核心
2002年第5期50-51,共2页
Thermal Power Generation