武汉机场飞行区土方调配大系统优化方案研究 被引量:1

The Large System Optimal Research On the Earth Work Allocation Program of Wuhan Airport's Flight Area
原文传递
导出
摘要 武汉机场是国家重点建设项目。本文提出了机场飞行区土方工程的最优调配问题。它是一个规模庞大的大系统最优规划,变量多达一千四百九十六个,一般计算机容量已不够。为此,在工民建施工领域首次提出了大系统土方调配优化数学模型进行优化,得出的优化方案可节约经费1073441.29元。所建立的大系统土方调配优化数学模型对工民建等大型土方调配优化有普遍的应用价值。 Wuhan Airport is an important construction subject in our country. This text has put for- ward the optimal allocation programme of this airport’s flight-area earthwork.it is a Large Scale System optimal plan which has 1496 variables, the ordinary computer’s capacity is not enough. For this reason, we first raise the Large System earthwork allocation optimal maths model in the field of industrial and civil building construction. According to this optimization, we can save 1073441.29 yan. Meanwhile, the maths model may suit all kinds of Large-scale industrial and civil artectical earthwork allocation problems, it has general application value.
出处 《系统工程理论与实践》 EI CSCD 北大核心 1994年第10期74-80,共7页 Systems Engineering-Theory & Practice
关键词 大系统 线性规划 目标函数 分解-协调 最优化 Large System Linear programming aim function resolration-coordination Optimization
  • 相关文献

参考文献2

  • 1郭元裕,白宪台,雷声隆,关庆滔,欧光华.湖北四湖地区除涝排水系统规划的大系统优化模型和求解方法[J]水利学报,1984(11).
  • 2汪应洛.系统工程导论[M]机械工业出版社,1982.

同被引文献4

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部