摘要
文章针对花园系统全停后恢复供电的各种方法进行分析 ,制定了黑起动方案 ,并对事故前后的系统运行方式进行了精心安排 ,从而快速恢复系统 ,以最大限度地对用户供电 。
The paper analyses varieties methods of restoring supply power after whole power cutting in Huyuan substation system,and establishes abnormal starting scheme,also gives a good arrangement to operate system running style,thereby restores system quickly and reduces electric energy loss.
出处
《青海电力》
2002年第3期21-22,44,共3页
Qinghai Electric Power