浅埋暗挖地铁施工地层沉降监测与控制 被引量:1

Ground Settlement Monitoring & Control in Metro Construction by Underground Cutting with Shallow Overburden
下载PDF
导出
摘要 地层沉降属多因一果。以广州地铁二号线公园前站—海珠广场站浅埋暗挖地铁区间地层沉降监测为实例 ,归纳分析了地层沉降的主要原因 ,提出了及时加强初期支护 (包括超前支护 )和应用注浆等辅助施工措施控制地层沉降结论 。 Introducing the actual conditions of the ground settlement monitoring in the running tunnels of Gongyuanqian Station~Haizhu Square Station of Guangzhou Metro Line 2, which is constructed by underground cutting method with shallow overburden, analyzing the primary causes of ground settlement, summarizing the accessorial technical measures, e.g. timely strengthening the initial support and variable grouting during tunneling to control the ground settlement. It is useful for theoretical research and application preference.
出处 《岩土工程技术》 2002年第5期256-259,279,共5页 Geotechnical Engineering Technique
关键词 地铁施工 浅埋暗挖 沉降监测 时间效应 初期支护 注浆工艺 underground cutting with shallow burden settlement monitoring time effect initial(beforehand)support grouting method
  • 相关文献

参考文献2

  • 1翁汉民.地下工程量测与试验[M].成都:西南交通大学出版社,1989.30.
  • 2钟桂彤.铁路隧道[M].北京:中国铁道出版社,1996.65-66.

共引文献6

同被引文献12

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部