期刊文献+

地铁车站与下穿桥结构一体化施工数值分析

Analysis of Integrated Construction for Subway Station and Underpass Bridge
下载PDF
导出
摘要 典型施工工艺条件下,地铁车站与下穿桥结构一体化施工的相关研究较少。本文采用有限元软件MIDAS/GTS对合肥地铁一号线某地铁站的深基坑工程的施工过程采用分段明挖顺作法进行数值模拟分析,并将地表沉降模拟结果与监测数据进行比较。研究表明:长条形地铁车站明挖+局部盖挖+分段分层对称的复合开挖方式对地表沉降的影响较小,且开挖面的转移会使地表沉降产生突变。该结论可为今后合肥类似的地铁车站建设提供参考。 Under the condition of typical construction technology,there is little research on the integratedconstruction of the metro station and the underbridge structure.The finite element software MIDAS/GTS wasadopted to make a numerical simulation of the deep foundation pit of Hefei metro 1# station,and the simulationresults were compared with the monitoring settlement data.Analysis showed that the complex excavation methodconsisting of open excavation of long strip subway station,covered excavation,and the symmetrical segmentation andlayer method had smaller effect on the ground surface settlement,and the transfer of excavated surfaces influencedthe surface subsidence.The conclusion can provide reference for the construction of similar subway station in Hefeiin the future.
作者 郭小娜 程桦 盛飞国 GUO Xiaona;CHENG Hua;SHENG Feiguo(School of Civil Engineering,Anhui Jianzhu University, Hefei, 230022, China;Anhui University Hefei, 230031, China)
出处 《安徽建筑大学学报》 2016年第3期12-16,共5页 Journal of Anhui Jianzhu University
关键词 地铁车站 深基坑 地表沉降 数值模拟 监测 metro station deep foundation pit ground surface settlement numerical simulation monitoring
  • 相关文献

参考文献6

二级参考文献26

  • 1龚晓南.关于基坑工程的几点思考[J].土木工程学报,2005,38(9):99-102. 被引量:200
  • 2金石嵩.地下连续墙在地铁站深基坑支护中的应用[J].工程建设与设计,2006(3):42-44. 被引量:7
  • 3铁建设函[2005]285号,新建时速200公里客货共线铁路设计暂行规定[S].
  • 4铁运函[2004]120号.铁路桥梁检定规范[S].[S].,..
  • 5GB50157-2003.地铁设计规范[S].[S].,..
  • 6JTGD602004,公路桥涵设计通用规范[s].
  • 7JGJ120-2012,建筑基坑支护技术规程[S].
  • 8GB50009-2012,建筑结构荷载规范[S].
  • 9刘皆谊.城市立体化发展与轨道交通[D].南京:东南大学,2012.
  • 10宋冰晶.地铁车站与立交结合设计[J].工程建设,2011,24(6):78-81.