马脊梁煤矿西三回风立井主要通风机启用后石炭系通风阻力大,不利于盘区正常回风及主要通风机的正常运转,为形成科学合理的通风系统,对西三回风立井主要通风机担负区域进行了全开路的调风及补掘回风巷,降低了矿井通风阻力,增强了矿井通风系统抗灾变能力。
After the use of the main fan of West third return air shaft in Majiliang Coal Mine, the ventilation resistance of the Carboniferous is large, and is not conducive to the normal ventilation of the panel and the normal operation of the main ventilator, to form the scientific and reasonable ventilation system, by adjusting air and supplementary extracting the return air roadway in the area undertaken by the main fan of West third return air shaft, reducing mine ventilation resistance, enhance the disaster resistance capability of mine ventilation system.
作者
邱晓东
高喜艮
Qiu Xiao-dong;Gao Xi-gen(Shanxi province Datong Coal Group Co Majiliang Coal Mine , Shanxi Datong 037027)
出处
《山东煤炭科技》
2017年第2期101-102,共2页
Shandong Coal Science and Technology
关键词
全开路调风
补掘回风巷
回风降阻
adjusting all ventilation way
extracting return air roadway
reducing return air resistance