基于仿真的室内装焊工场分段建造方案评估与优化

Evaluation and Optimization of Simulation Based Block Construction Scheme for Indoor Assembly in Welding Workshop
下载PDF
导出
摘要 基于仿真的生产调度方法,以室内装焊工场的分段建造(含分段总组)为研究对象建立三维仿真模型,通过仿真模拟输出仿真运行数据,实现对特定建造方案下的物量、场地利用率及生产计划等参数的准确评估。针对建造方案中的不合理之处,通过采用基于序列的优化方法对生产计划及场地布局等进行优化。实例分析结果表明,该优化方法可缩短分段建造周期、提高场地利用率,从而为生产计划的制定和生产调度水平的提升提供支持。 This study establishes a 3D simulation model for the block construction (including section assembly) of indoor assembly in welding workshop based on the production scheduling simulation method. Accurate evaluation of production capacity, space utilization, production plan and other parameters for the specific construction can be achieved with the simulation data and the production plan and space arrangement are optimized with a sequence based optimization method to rectify the inappropriateness. The result of the analysis on some examples shows that the proposed optimization method can reduce the block construction cycle, increase space utilization, and thus provide support to the production plan making and to the improvement of production scheduling.
作者 朱明华 李沛田 单小芬 毛申飞 朱仁贵 ZHU Ming-hua;LI Pei-tian;SHAN Xiao-fen;MAO Shen-fei;ZHU Ren-gui(Jiangnan Shipyard (Group) Co., Ltd., Shanghai 201913, China;CSSC Huangpu Wenchong Shipbulding Co., Ltd., Guangzhou 510715, China)
出处 《船舶与海洋工程》 2017年第1期43-47,共5页 Naval Architecture and Ocean Engineering
基金 国防科工局基础科研项目(A0720132011)
关键词 仿真 室内装焊工场 分段建造 simulation indoor assembly in welding workshop block construction
  • 相关文献

参考文献2

二级参考文献18

  • 1潘徐杰,蒋志勇.中间产品纳期计划研究[J].船舶工程,2006,28(6):37-40. 被引量:2
  • 2PARK K, LEE K, PARK S, et al. Modeling and solving the spatial block scheduling problem in a shipbuilding company [J]. Computers and Industrial Engineering, 1996, 30 (3) : 357-364.
  • 3NEUMANN R J. Network scheduling developmant in an MRHI environment[J]. Journal of Ship Production, 1994,10(4) : 115-123.
  • 4LEE T E, SONG J S. Searched based heuristic algorithms for basic planning in a large shipyard[J]. Journal of Ship Produc- tion, 1996,12(4) :268-274.
  • 5ALFELD L E, PILLIOD C S, W1LKINS J R. A simulation model of the shipbuilding process[J]. Journal of Ship Produc- tion, 1988,14(1) : 33-40.
  • 6PRASAD V R, GRAUL M, BENJAMIN P, et al. Resourceconstrained shop-level scheduling in a shipyard[J]. Journal of Ship Production, 2003,19 (2) : 65-75.
  • 7张浩,樊留群,马玉敏.数字化工厂技术和应用[M].北京:机械工业出版社,2006:93-99.
  • 8Park K, Lee K, Park S, et al. Modeling and solving the spatial block scheduling problem in a shipbuilding company [J]. Computers Industrial Engineering, 1996, 30(3) : 357-364.
  • 9Shin Jong Gye, Kwon Oh Heung, Ryu Cheolho. Heuristic and metaheuristic spatial planning of assembly blocks with process schedules in an assembly shop u- sing differential evolution [J]. Production Planning and Control, 2008, 19(6):605-615.
  • 10Varghese Ranjan, Young Yoon Duck. Dynamic spatial block arrangement scheduling in shipbuilding industry using genetic algorithm[C]//Proceedings of the 3rd International IEEE Conference on Industrial Informatics. Perth, Australia:lEEE Press, 2005 : 444-449.

共引文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部