摘要
在已建船闸旁增建二线船闸,应综合考虑相邻建筑物安全性、通航水流条件、施工条件及工程投资等因素。以红花二线船闸平面布置为例,在分析已建枢纽布置及结构物特点的基础上,确定二线船闸工程建设目标。重点论述二线船闸建设时选址及平面布置思路及方法,并对不同方案进行技术经济方案比选,对增建二线船闸工程的项目具有借鉴意义。
The safety of the existing structures,flow conditions,construction conditions and investment should be considered if building a new ship lock next to the one already built.Taking Honghua second-line ship lock for example,we analyze the layout of the existing hydropower complex and characteristics of the existing structures,and determine the construction object of the second-line ship lock.The principles and methods of site selection and planning are expounded,and technical and economic comparison is conducted among different schemes,which may serve as reference for similar projects.
作者
宁武
姜兴良
NING Wu;JIANG Xing-liang(CCCC Water Transportation Consultants Co., Ltd., Beijing 100007, China)
出处
《水运工程》
北大核心
2017年第9期165-170,共6页
Port & Waterway Engineering
关键词
二线船闸
平面布置
轴线布置
second-line ship lock
general layout
axial arrangement