为了提高核电项目建造过程风险评价的准确度,针对其风险评价过程中存在的诸多不确定性因素,应用未确知测度理论,建立核电项目建造过程风险评价模型。选用项目施工因素、进度因素、费用控制因素和环境因素等4个因素作为一级指标,项目质量等13个因素作为二级指标,构建评判要素的未确知测度函数;同时采用信息熵理论确定评价要素权重,最后依据置信度识别准则对核电项目建造过程风险等级进行判定。研究结果表明:该核电项目建造过程风险性等级为一般级别风险,与实际情况吻合。该方法可为科学评价核电项目建造过程风险提供一种新思路,为类似项目的风险评估提供参考和借鉴。
In order to improve the accuracy of the nuclear power project construction process risk analysis,and in view of the uncertainty factors in the process of risk analysis,a nuclear power project construction process risk analysis model was set up with applying of the uncertainty measurement theory.Four factors,such as project construction factor,schedule factor,cost control factor and environment factor,are selected as the first level indicators,and the13factors such as project quality are taken as the second level indicators to construct the unascertained measurement function of the evaluation factors.The weight of evaluation factors were determined by the information entropy theory and the nuclear power project construction process risk level was finally determined on the basis of confidence level recognition criteria.The research results show that nuclear power project construction processs risk level is the general level risk,and it coincides with the actual situation.This method can provide a new idea for the scientific evaluation of the risk of the nuclear power project construction process,and provide reference for the risk assessment of similar projects.
作者
蒋复量
张帅
李向阳
康虔
JIANG Fu liang;ZHANG Shuai;LI Xiang yang;KANG Qian(University of South China,Hengyang 421001,China)
出处
《南华大学学报(社会科学版)》
2017年第5期6-10,共5页
Journal of University of South China(Social Science Edition)
基金
国家安监总局安全生产重大事故防治关键技术科技项目"铀矿深部开采辐射安全技术与装备研究"资助(编号:hunan-0022-2015AQ)
南华大学研究生科研创新项目"循环动载荷作用下铀尾砂充填体氡析出机理研究"资助(编号:2016XCX24)
关键词
核电项目
未确知测度
信息熵
风险评价
nuclear power project
uncertainty measurement
entropy of information
risk assessment