大型多筒体四边形塔架式火炬吊装技术 被引量:7

Hoisting technique ofmulti-cylinder quadrilateral flare tower
下载PDF
导出
摘要 神华宁煤400万t/a煤炭间接液化项目全厂外管下游火炬系统,为一座150 m高的多筒体四边形塔架式火炬,吊装难度大。经论证火炬塔架采用分段正装方法,火炬筒体采用吊车倒装方法,可解决吊装难题。在简要介绍了工程概况,论证了工程采取的吊装方法之后,较为详细地阐述了包括吊装总体思路、塔架吊耳、塔架吊装软加固、吊装索具、临时操作平台制作、导轨吊装、火炬筒体吊装等施工工艺。实践证明,采取上述吊装方法,吊装一次取得了圆满的成功。 The flare system of400×104t/a coal indirect liquefaction project in SNCG is a150m multi-cylinder quadrilateral flare tower.The reasonable argument presents the construction methods to overcome difficult hoisting problem,i.e.the quadrilateral flare tower frame is assembled with sections,and the cylinders are invertedly assembled by using a crane.This paper illustrates the whole hoisting plan and concrete measures related to lifting lugs of tower frame,tower frame soft reinforcement,rigging for hoisting,temporary operation platform,guiding rail hoisting,flare cylinder hoisting,and so on.The multi-cylinder quadrilateral flare tower is successfully hoisted according to above mentioned methods.
作者 关启军 刘树君 冯庆辉 付恒 GUANQijun;LIU Shujun;FENG Qinghui;FU Heng(China Petroleum Seventh Construction Co.,Ltd.,Qingdao 266300,China)
出处 《石油工程建设》 2017年第6期81-82,共2页 Petroleum Engineering Construction
关键词 塔架式火炬 多筒体 分段正装 吊车倒装 flare tower multi-cylinder assembly with sections inverted assembly by using crane
  • 相关文献

同被引文献20

引证文献7

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部