摘要
为减少人的失误,对核电厂主控室人机接口实施人因验证和确认工作。本文在实际核电项目经验的基础上,发现在平台上实现的人机界面与设计的人机界面存在偏差,因此,在开展最终确认活动前,进行实施验证活动,确保人机交互界面间的一致性。
In order to reduce the human errors,human factors engineering verification and validation(HFE V&V)activities should be performed in the main control room of the nuclear power plant(NPP).This paper is on the basis of the actual experience of nuclear power projects.The biases have been observed between the implemented human-system interfaces(HSI)and designed human-system interfaces.So it is necessary to perform the implementation verification(IV)activity before the final integrated system validation(ISV)activity to guarantee the consistency between the implemented human-system interfaces and designed human-system interfaces.
作者
王佳
蔡蕾
WANG Jia ;CAI Lei(Nuclear Control Systems Engineering Co., Ltd., Beijing, China 100176, China)
出处
《科技视界》
2018年第3期214-215,共2页
Science & Technology Vision
关键词
因工程验证与验证
人机界面
实施验证
Human factors engineering verification and validation
Human-system interface
Implementation verification