摘要
文章针对鞍钢鲅鱼圈1号高炉停炉过程的方法进行总结和介绍。通过对其休风料的准备,预休风过程等准备方法,以及停炉过程中对风量、水量、富氧、炉顶温度、煤气组成等控制实现了安全停炉的目的。整个过程共用时20h15min。
The method of blowout the furnace of No.1 blast furnace in Ba Yuquan of Ansteel was introduced.Through the preparation method of the preparation of its off wind material has been pre off the wind process,and the control of air volume,water quantity,oxygen enrichment,top temperature and gas composition in the process of stopping,the purpose of safe shutdown was achieved.The whole process of blowout the furnace was shared 20h15min.
作者
佟溥昊
戴永燕
蒋益
黄菊
白欣
Tong Puhao;Dai Yongyan;Jiang Yi;Huang Ju;Bai Xin(Education and Training Center,Anshan Iron and Steel Group Corporation;Bayuquan Branch Angang Steel Co.,Ltd)
出处
《冶金能源》
2018年第2期7-10,共4页
Energy For Metallurgical Industry
关键词
大型高炉
降料线
停炉
large sized blast furnace
dropping stock line
blowout the furnace