摘要
本文根据南梁煤矿3-1煤胶带大巷当时施工情况,在3-1煤胶带大巷中采取胶带叠放的方案安装钢丝绳芯带式输送机。笔者根据工作实际,对其安装方案和施工方法进行了探讨,以供同行交流与借鉴。
According to the construction condition of the 3-1 coal tape lane of Nanliang Coal Mine at that time,the steel wire rope belt conveyor was installed in the 3-1 coal belt laneway by the belt stacking scheme.According to the actual work,the author discussed the installation scheme and construction method for exchange and reference.
作者
范强
FAN Qiang(The Tenth Engineering Division of China Coal First Construction Co.,Ltd.,Handan 056003,China)
出处
《价值工程》
2018年第13期174-175,共2页
Value Engineering
关键词
带式输送机
安装
叠放
硫化
belt conveyor
installation
stacking
vulcanization