摘要
本文针对暴雨强度公式问题,以土耳其某电站项目的水文资料为基础利用年最大值法,拟合对应的暴雨强度公式,并对基础资料的要求,模拟结果的误差等进行分析调整。本文还探讨了无暴雨强度公式导致厂区雨水设计不精确的问题,对今后涉外项目雨水排水设计有一定的指导作用。
Hydrological data of a foreign country is used to simulate the Rainstorm intensity formula based on annual maximum value method in this paper.Requirement of hydrological data and deviation of simulation are analyzed.Design inaccuracy of rain water drainage for foreign thermal power plant is preliminary discussed and annual maximum value method is used to simulate rainstorm intensity formula in this paper,which is instructive for rain water drainage design of foreign projects.
作者
魏巍
张捷
WEI Wei;ZHANG Jie(Central Southern China Electric Power Design Institute,Wuhan 430072,China;China Sinogy Electric Engineerng Co.,Ltd.,Shanghai 200061,China)
出处
《电力勘测设计》
2018年第4期17-20,共4页
Electric Power Survey & Design
关键词
国外火力发电
暴雨强度公式
雨水排水
年最大值法
foreign thermal power plant
rainstorm intensity formula
rain water drainage
annual maximum value method