根据中哈天然气管道实际情况,为保证建设工期和运行维护要求,从安全、可靠、实用等角度考虑,哈萨克斯坦压缩机站设计采用天然气发电机、配套自动化控制系统的自发电供电方案。阐述了负荷分析、发电机配置方案、发电站电气主接线方案、电站控制系统(ECS)的应用以及发电站假负载配置等技术要点。该技术极大地保证了电站的可靠性和稳定性。可为今后压缩机站项目自发电电站的设计和运行提供宝贵的经验。
According to the actual situation of Kazakhstan-China Gas Pipeline and in order to ensure the construction period and operation maintenance,the power supply design scheme for compressor stations in Kazakhstan-China Gas Pipeline adopts the natural gas generator and automatic control system for self-generating electricity after considering the safety,reliability,practicability and other factors.This paper illustrates the technical key points including load analysis,generator configuration scheme,power station electrical main wiring scheme,electric control system(ECS)application,dummy load configuration.It provides a strong guarantee for the safe and reliable operation of the power station.
作者
孙文博
成闻
刘艳鹏
樊宝华
王雪华
SUN Wenbo;CHENG Wen;LIU Yanpeng;FAN Baohua;WANG Xuehua(Sino-pipeline International Company Limited,Beijing 100007,China)
出处
《石油工程建设》
2018年第2期51-55,共5页
Petroleum Engineering Construction
关键词
压缩机站
天然气发电机
电站控制系统(ECS)
compressor station
natural gas generator
electric control system(ECS)for power station