摘要
通过对500 kV塔拉变电站220 kV双母线双分段改造方案的分析,指出改造过程中存在的主要风险点及不安全因素,提出相应的控制措施及改进建议,为今后500 kV变电站220 kV双母线双分段改造工程的方案制定和实施提供参考。
Through the analysis of220kV double bus double segment modification project in500kV Tala substation,pointed out the risk and unsafe factors in the process of modification,put forward control measures,and some reasonable improvement suggestions to provide a reference for scheme formulation and implement to220kV double bus and double segment modification in500kV substation.
作者
杨成刚
巴特尔
萧丽
YANG Chenggang;Bateer;XIAO Li(Inner Mongolia EHV Power Supply Bureau, Hohhot 010080, China;Inner Mongolia Power(Group) Co.,Ltd., Hohhot 010020, China)
出处
《内蒙古电力技术》
2018年第2期36-38,42,共4页
Inner Mongolia Electric Power
关键词
变电站
双母线双分段
母线差动保护
二次接线
substation
double bus double segment
bus differential protection
secondary wiring