摘要
以山西省某供电分公司生产调度综合楼空调设计为基础,介绍了该工程的冷热源和空调风系统。重点介绍了冰蓄冷中央空调系统的设计和运行模式。结合分时电价政策,确定蓄冰时间,计算了机组和蓄冰装置容量,从而得到设计日空调负荷分配情况。
On the basis of the air conditioning system design for the production and dispatching complex building in a power supply branch of Shanxi Province,the cold and heat source and air conditioning wind system of the project are introduced.This paper focuses on the design and operation mode of the ice storage central air conditioning system.Define ice time combined with the TOU electricity prices of Jiangsu province and calculate the capacity of main engine and ice-storage devices.Thus,get hourly air-condition load distribution.
作者
任晓东
李德贤
REN Xiao-dong;LI De-xian(The Architectural Design&Research Institute of Zhejiang University Co.,Ltd.;Zhejiang College of Construction)
出处
《建筑热能通风空调》
2018年第5期94-96,103,共4页
Building Energy & Environment
关键词
冰蓄冷空调
运行模式
蓄冰装置容量
空调负荷
ice-storage air-condition system
operating mode
capacity of ice storage device
air conditioning load