摘要 本文针对国内某大型深水导管架结构总装的实际需求,详细阐述了大型深水导管架结构总装垫墩的设计过程。采用ANSYS和SACS有限元软件分析与手工计算相结合的方法对垫墩进行设计和计算。此外,对垫墩强度、稳定性、水泥滑块强度和地基承载力等部分也进行了校核分析。 According to the general assembly requirement for a large deepwater jacket project in China,the design process of general assembly support was described in detail,including the combination of finite element analysis(ANSYS&SACS)and hand calculation applying to the above design.Meanwhile,the reaction of support was calculated by taking the multi-point failure into account.In addition,a check analysis was made for the strength and stability of support,the strength of cement sliders and the foundation bearing capacity.
作者 吴强 郭宁 Wu Qiang;Guo Ning(COOEC Qingdao Co.,Ltd.,Qingdao Shandong 266520,China)
出处 《港工技术》 2018年第4期29-32,共4页 Port Engineering Technology
关键词 导管架 总装垫墩 有限元 深水 建造 jacket general assembly support finite element deepwater construction
  • 相关文献

参考文献2

二级参考文献2

  • 1American Petroleum Institute. API recommended practice 2A-WSD (RPgA-WSD) [S]. Twenty-First Edition, 2000. Stress Design and Plastic Design[S]. 2005.
  • 2American Institute of Steel Construction (AISC). Specification for Structural Steel Buildings - Allowable.