摘要
大口径管道在江南水网地区施工时,地表下多为淤泥或烂泥,地基承载力极差,开挖管沟常因塌方、清淤等作业,造成管沟沟底宽度加大,且清淤作业需多台设备同时施工,造成作业带超宽。对水网地区作业带超宽成因进行了分析,并对其处理方式进行了研究,为后续江南水网地区作业带宽度设计及施工提供了借鉴。
In the construction of large diameter pipelines in Jiangnan water network area,the ground surface was mostly silt or mud;the bearing capacity of the foundation was very poor.The excavation pipe ditch often caused by the collapse and dredging and so on,induced the width of the bottom of the ditch,and the dredging operation needed to be constructed at the same time,by which an ultra wide operation belt was produced.In this paper,the cause of super-wide operation belt in water network area is analyzed,and its treatment mode is studied,which provides a reference for the design and construction of wide operation belt in Jiangnan water network area.
作者
董国忠
刘新生
张博
潘亚银
王爱东
Guozhong Dong;Xinsheng Liu;Bo Zhang;Yayin Pan;Aidong Wang(No.4 Branch Company of China Petroleum Pipeline Engineering Co.Ltd.,Langfang Hebei;China Petroleum Pipeline Machinery Manufacture Co.Ltd.,Langfang Hebei)
出处
《石油天然气学报》
CAS
2018年第3期126-128,共3页
Journal of Oil and Gas Technology
关键词
水网地区
作业带超宽
长输管道施工
Water Network Region
Super Wide
Construction of Long-distance Pipeline