基于PBIL算法的炼钢生产低碳调度问题 被引量:1

Low-carbon scheduling problem in steelmaking production based on PBIL algorithm
下载PDF
导出
摘要 为了将碳排放引入生产调度优化,针对其等待时间受限的生产调度问题,建立最小化最大完工时间与碳排放的双目标优化模型,利用加权效用函数与标准化方法将其转换为单目标,并采用种群增量学习算法对问题进行求解。仿真实验表明,作业等待时间因受上限约束对碳排放影响较小,设备空转是影响碳排放的主要因素,提高设备利用率可有效减少碳排放;最大完工时间与碳排放呈反相关关系,即为尽快响应客户要求企业需付出较大的碳排放代价,而在碳权交易市场下企业为降低碳排放成本需适当放宽以往的经济指标。 To introduce carbon emission into production scheduling optimization,aiming at the production scheduling problem with limited waiting time,a dual-objective optimization model for minimizing makespan and carbon emissions was constructed,and it was rebuilt as a single-objective model by using weighting utility function and standardized method.In addition,an Improved population-based increased learning(IPBIL)was utilized to solve the problem.Extensive simulation was conducted and the results showed that the operation waiting time had little impact on carbon emissions and lots of carbon were generated with equipment idling,thus the carbon emission could be reduced effectively by improving the utilization rate of the equipment.Moreover,makespan was inversely related to the carbon emission that enterprises needed to pay a greater cost of carbon emissions to quick respond to customer requirements,but they should relax economic indicators to reduce the cost of carbon emissions in carbon rights trading.
作者 张燕华 陈伟达 孟祥虎 ZHANG Yanhua;CHEN Weida;MENG Xianghu(School of Economics and Management,Southeast University,Nanjing 211189,China;School of Information Engineering,Tibet University For Nationalities,Xianyang 712000,China;School of Automation,Southeast University,Nanjing 211189,China)
出处 《计算机集成制造系统》 EI CSCD 北大核心 2018年第10期2407-2414,共8页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金面上资助项目(71271054 71571042) 国家自然科学基金青年资助项目(71501046)~~
关键词 种群增量学习算法 生产调度 碳排放 最大完成时间 population-based increased learning algorithm production scheduling carbon emissions makespan
  • 相关文献

参考文献7

二级参考文献78

  • 1王文科.乙醇和甲醇混合液激光拉曼光谱研究[J].北京化工大学学报(自然科学版),1995,22(4):81-85. 被引量:10
  • 2汪存富,蔚承建.一种新的求解ATSP问题的PBIL算法[J].计算机工程与应用,2005,41(27):66-68. 被引量:4
  • 3李铁克,周健,孙林.连铸连轧和冷装热轧并存环境下的炼钢-连铸生产调度模型与算法[J].系统工程理论与实践,2006,26(6):117-123. 被引量:18
  • 4周树德,孙增圻.分布估计算法综述[J].自动化学报,2007,33(2):113-124. 被引量:209
  • 5姚新 陈国良 等.进化计算机研究[J].计算机学报,1995,9(18):694-705.
  • 6Tang,L. X. , Liu, J. Y. , Rong,A. Y. , et al. A mathematical programming model for scheduling steelmakingcontinuous casting production[J]. European Journal of Operational Research, 2000, 120(2): 423-435.
  • 7Tang, I.. X. , Luh, P. B. , I.iu, J. Y. , et al. Steelmaking process scheduling using lagrangian relaxation [J]. International Journal of Production Research,2002, 40(1): 55-70.
  • 8Xuan, H. , Tang, L. X.. Scheduling a hybrid flowshop with batch production at the last stage[J]. Computers and Operations Research, 2007, 34(9): 2718-2733.
  • 9Bellabdaoui, A. , Teghem, J.. A mixed-integer linear programming model for the continuous casting planning [J]. International Journal of Production Economics,2006, 104(2): 260- 270.
  • 10Missbauer, H. , Hauber, W. , Stadler, W.. A scheduling system for the steelmaking continuous process: A case study from the steel-making industry[J]. International Journal of Production Research, 2008, First, 1- 26.

共引文献77