控制工后沉降条件下堆载预压地基处理参数的优化 被引量:1

Optimization of treatment parameters by surcharge preloading under the controlling condition of post-construction settlement
下载PDF
导出
摘要 在打设排水板的堆载预压地基处理中,当施工工期受限时,排水板间距和堆载厚度是影响地基处理效果的两大主要因素,需进行工程设计优化,不仅应满足地基处理要求,且尽可能降低工程造价。以上海南汇某陆域地基处理工程为例,以工后沉降为控制条件,以经济效益为目标,采用Matlab编程对排水板间距和堆载厚度进行优化设计。该方法可考虑各种可能的参数组合,高效可靠,便于应用,不仅达到了设计要求,而且可获得更好的经济效益。 When the drainboards are used in preloading ground treatment with surcharge and the construction period is limited,the spacing of drainboards and the surcharge thickness are the two main factors affecting the effect of treatment.It is necessary to optimize the engineering design to meet the requirements of ground treatment,and reduce the project cost as much as possible.In this paper,taking a ground treatment project in Nanhui of Shanghai as the example,we carried out the optimization of the spacing of drainboards and the surcharge thickness using Matlab programming,with the post-construction settlement as the controlling condition and the economic benefits as the goal.The method can consider all kinds of possible parameter combinations,and it's efficient,reliable and convenient for application.It meets the design requirements,and achieves better economic benefits.
作者 宋艳 SONG Yan(CCCC-Shanghai Waterway Engineering Design and Consulting Co.,Ltd.,Shanghai 200120,China)
出处 《中国港湾建设》 2018年第11期34-36,51,共4页 China Harbour Engineering
关键词 堆载预压 地基处理 工后沉降 塑料排水板 固结度 preloading with surcharge of fill ground treatment post-construction settlement plastic drainboard consolidation degree
  • 相关文献

参考文献1

二级参考文献5

  • 1谢康和,曾国熙.砂井地基的优化设计[J].土木工程学报,1989,22(2):3-12. 被引量:13
  • 2.京沪高速铁路线桥隧站设计暂行规定[S].[S].铁道部第三勘察设计院等,2002..
  • 3地基处理编写委员会.地基处理手册[M].北京:中国建筑出版社出版,2000,9..
  • 4MICHALEWICZ Z.Genetic algorithm+Data structures=Evolution programs[M]. AI Series. New York:Springer-Verlag,1994.
  • 5潘秋元,朱向荣,谢康和.关于砂井地基超载预压的若干问题[J].岩土工程学报,1991,13(2):1-12. 被引量:39