建筑施工中的两阶段学习曲线模型 被引量:4

Two-stage Learning Curve Model in Construction
下载PDF
导出
摘要 通过对实际工程现场数据的收集,获取了钢筋现场加工与安装、模板安装与拆除、混凝土浇筑等工作的原始数据,据此研究我国建筑施工领域操作者的学习效应。工作效率变动图表明随着单元数目的增加,各工作的施工效率均大幅提升,表明了学习效应的客观存在;计算出的各工作学习率在83%~95%之间,其中模板工作的手工操作强度大,学习效应最明显;运用Origin软件绘制出的学习曲线区分下降和稳定阶段,据此提出了学习曲线两阶段模型,该模型能显著改善已有模型预测性能欠佳的不足。本文研究成果为学习效应在建筑施工领域的应用奠定了理论和实践基础,为工程项目进度、成本管理提供了新的思路。 The learning effect in Chinese construction projects are analyzed through base data of processing and installation of steel bars,installation and removal of formwork,concrete pouring.With the number of repetitive units increasing,the production rates of these works are enhanced substantially,which shows the objective existence of learning effect.The learning rates of above works are calculated according to learning effect theory.The calculation results are between eighty-three to ninety-five percent and the learning effect of formwork is most obvious because the manual operation in it is intensity.The learning curves plotted by Origin can be divided into two stages,namely,downward stage and stable stage.Based on this result,a two-stage learning curve model is proposed in this paper.The shortcoming of poor prediction performance in existing model will be improved significant in this model.Empirical research results in this paper lay theory and practice foundation for the application of learning effect in construction field.
作者 蒋红妍 王鑫业 彭颖 JIANG Hong-yan;WANG Xin-ye;PENG Yin(School of Civil Engineering,Xi’an University of Architecture and Technology,Xi’an 710055,China)
出处 《土木工程与管理学报》 北大核心 2018年第6期43-49,共7页 Journal of Civil Engineering and Management
基金 国家自然科学基金(51408459)
关键词 实证研究 重复性项目 工作效率 学习效应 学习曲线 empirical research repetitive project production rate learning effect learning curve
  • 相关文献

参考文献1

二级参考文献25

  • 1Harris R B,Ioannou P G. Scheduling projects with re- peating activities [ J ]. Journal of Construction Engi- neering and Management, 1998,124(4) :269-278.
  • 2Lucko G. Productivity scheduling method:Linear sched- ule analysis with singularity functions [ J ]. Journal of Construction Engineering and Management, 2009,135 (4) :246-253.
  • 3Kallantzis A, Soldatos J, Lambropoulos S. Linear ver- sus network scheduling: a critical path comparison [ J ]. Journal of construction engineering and management, 2007,133 (7) :483-491.
  • 4Zhang Lihui ,Pan Chuyun ,Zou Xin. Criticality compari- son between the repetitive scheduling method and the network model[ J ]. Journal of Construction Engineer- ing and Mana-gement ,2013,139(10) :135-141.
  • 5Hyari K H, E1-Rayes K, E1-Mashaleh M. Automated trade-off between time and cost in planning repetitive construction projects [ J ]. Construction Management and Economics ,2009,27 (8) :749-761.
  • 6Georgy M E. Evolutionary resource scheduler for linear projects [ J ]. Automation in Construction, 2008, 17 (5) :573-583.
  • 7Tang Y, Liu R, Sun Q. Study and Application on China Railway Construction Project Scheduling Model Based on Resource Leveling [ M ]. Berlin : Springer Berlin Heidelberg, 2013.
  • 8De P,James Dunne E, Ghosh J B,et al. The discrete time-cost tradeoff problem revisited [ J ]. European Journal of Operational Research, 1995,81 ( 2 ) : 225- 238.
  • 9Hindelang T J,Muth J F. A dynamic programming al- gorithm for decision CPM networks [ J ]. Operations Research, 1979,27 (2) :225-241.
  • 10Hazlr O, Haouari M, Erel E. Discrete time/cost trade- off problem: a decomposition-based solution algorithm for the budget version [ J ]. Computers & Operations Research, 2010,37 (4) : 649-655.

共引文献1

同被引文献32

引证文献4

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部