摘要
通过分析哈尔乌素露天煤矿中间搭桥施工流程,计算得到搭桥准备时间、搭桥时间以及拆桥时间。在考虑各流程之间的逻辑关系基础上,结合生产实际,得到搭桥全流程时间。最后采用甘特图对露天矿中间搭桥流程进行描述,为哈尔乌素露天煤矿今后搭桥组织管理提供可靠依据。
By analyzing the bridging construction process in Ha'erwusu Open-pit Coal Mine,the article calculates the preparation time for bridging,bridging time and demolition time.On the basis of the logical relationship between the various processes,the mine obtains full process time of the bridging by combining the production practice.In the end,the article uses Gantt chart to describe the bridging process in the open-pit mine,so as to provide a reliable basis for the management of Ha'erwusu Open-pit Coal Mine in the future.
作者
田培忠
TIAN Peizhong(Ha'erwusu Open-pit Coal Mine,China Shenhua Energy Co.,Ltd.,Ordos010300,China)
出处
《露天采矿技术》
CAS
2018年第6期19-23,共5页
Opencast Mining Technology
关键词
中间搭桥
流程规划
甘特图
施工
露天煤矿
middle bridging
process planning
Gantt chart
construction
open-pit coal mine