摘要
虎门二桥坭洲水道桥为主跨1 688m的不对称双塔钢箱梁悬索桥,全桥共4套主索鞍总成,主索鞍鞍体为铸焊结构,由2个半鞍体通过高强度螺栓锁合而成,半鞍体重达125t,安装在256.4m高的塔顶主鞍室内。主索鞍采用"桥塔承台顶面转放平台移运+塔顶门架承载+连续提升液压千斤顶垂直起吊+重物移运器纵移"的方式吊装。施工时,首先采用塔顶门架起吊系统吊装格栅及反力架,精确定位后浇筑格栅反力架混凝土,然后利用塔顶门架起吊系统吊装上、下承板,最后采用塔顶门架起吊系统分别吊装2个半鞍体至塔顶,利用高强度螺栓将2个半鞍体拼接成整体。在主桥上部结构安装过程中,根据主索鞍预偏监控指令,采用2个1 000t千斤顶逐步将其顶推到位,完成主索鞍的最终定位与安装。
The Nizhou Waterway Bridge of the Second Humen Bridge is an asymmetrical double-tower steel box girder suspension bridge with the main span of 1 688 m.The bridge consists of four main cable saddles,and the main cable saddles have a structure of cast welding that consists of two semi-saddles locked by high-strength bolts.The semi-saddles with the weight of 125 t are installed in the main saddle chamber at the top of a 256.4 m-high tower.The main cable saddles are hoisted by means of"transfer platform on the top of bridge pylon cap+support by portal frame on pylon top+vertical hoist by a hydraulic jack with continuous lifting+longitudinal translation by transporter".During the construction,the grid reaction frame is hoisted by a hoisting system on the tower top,and concrete grout is poured into the grid reaction frame after being precisely positioned;then the upper and lower supporting plates are hoisted by the hoisting system on the tower top;finally,two semi-saddles are hoisted to the top of the tower by the hoisting system on the tower top and joined together by the high-strength bolts.During the installation of the superstructure of the main bridge,according to the pre-deflection monitoring instructions,the main saddles are gradually pushed in place by two 1 000 t jacks,thus final positioning and installation of the main saddles are completed.
作者
童俊豪
朱超
代希华
TONG Jun-hao;ZHU Chao;DAI Xi-hua(The 2nd Humen Bridge Branch,Guangdong Provincial Highway Construction Co.,Ltd.,Guangzhou 511447,China)
出处
《桥梁建设》
EI
CSCD
北大核心
2018年第6期6-11,共6页
Bridge Construction
关键词
悬索桥
主索鞍
铸焊结构
门架吊装系统
吊装施工
精度控制
施工技术
桥梁施工
suspension bridge
main cable saddle
structure of cast welding
gantry hoisting system
hoisting and installation construction
accuraly control
construction technique
bridge construction