针对设计变更后的公路石方路堑工程,设计制定侧墙支架台车,结合既有承建工程实际情况,分析其施工效率及实用性,达到保质保量,按期完工的目的。
For the highway stone roller construction after the design change,the side wall bracket trolley is designed.Combined with the actual conditions of the existing construction project,the construction efficiency and practicability are analyzed,in order to make the project completed on schedule with quality and quantity guaranteed.
作者
张志远
ZHANG Zhi-yuan(China Railway 16th Bureau Group the 5th Engineering Co.,Ltd.,Tangshan 063000,China)
出处
《价值工程》
2019年第1期117-120,共4页
Value Engineering
关键词
公路路堑
设计变更
侧墙支架台车
highway roller
design change
side wall bracket trolley