摘要 利用废弃矿洞建设抽水蓄能电站不仅是抽水蓄能新形式的探索,更是基于电力市场和生态环境恢复双向需求的产物。在明确定义三种矿洞(坑)利用模式的基础上,重点从矿洞抽水蓄能的站址选择、动能估算、工程布置三个方面进行了工程技术可行性分析,并在典型案例中予以验证,旨在为进一步设计优化矿洞抽水蓄能工程布置方案提供借鉴。 Utilizing the abandoned mine to construct pumped storage plant is not only a new form of exploration,but also a bidirectional product on account of the demand of power market and ecological environment restoration.Based on the clear definition of three utilization patterns to different mines,three aspects including mine site selection,kinetic energy estimation,and project layout have been researched and verified in the typical case in the technical feasibility analysis.And the purpose of this paper is to provide reference for further design and project layout optimization of pumped storage plant utilizing abandoned mine.
作者 王婷婷 曹飞 唐修波 李阳 张昊晟 WANG Tingting;CAO Fei;TANG Xiubo;LI Yang;ZHANG Haosheng(Power China Beijing Engineering Corporation Limited,Beijing 100024,China)
出处 《储能科学与技术》 CAS CSCD 2019年第1期195-200,共6页 Energy Storage Science and Technology
基金 国家电网公司部总部科技项目资助(NY71-17-002)
关键词 废弃矿洞 抽水蓄能电站 利用模式 全地下 煤矿 abandoned mine pumped storage plant utilization patterns underground coal mine