期刊文献+

基于shapley值的PPP项目风险分担设计 被引量:1

The design of risk allocation in PPP projects on the basis of shapley
下载PDF
导出
摘要 PPP项目大多风险较高,政府与社会资本作为风险的主要承担者,应合理分担风险。在文献梳理的基础上,建立基于shapley值的PPP项目风险分担模型,并通过案例进行分析。研究认为政府与社会资本应共担风险,但风险并不是平均分配,并提出相关建议。 There is more risk in PPP projects,the reasonable risk allocation should be designed for the public and private sections. The risk allocation in PPP projects on the basis of shapely was constructed after the literature review,and analyzed through the case study. We find that the public and private sections should share the risk,but not equally. And some suggestions are proposed.
作者 高辉 李栋 Gao Hui;Li Dong(College of Economics & Management, Zhejiang University of Technology, Hangzhou 310023, China)
出处 《山西建筑》 2019年第3期231-232,共2页 Shanxi Architecture
基金 浙江省自然科学基金项目(LY15G030029) 国家社科基金年度项目(17BJY168)资助
关键词 PPP SHAPLEY值 风险分担 Public-Private Partnership shapely risk allocation
  • 相关文献

参考文献1

二级参考文献4

  • 1Zhang, X.Q. and Mohan M. Kumaraswamy,Procurement Protocols for Public-Private Partnered Projects. Journal of Construction Engineering and Management, 2001.
  • 2Marcus Ahadzi, Graemebowles, Public-Private Partnership and Contract Negotiations: an empirical study.Construction Management and Economics, 2004.
  • 3Ronsen, Oddvar Sten. Requirements of Successful Public Private Partnership Projects-Risk Allocation between the Private and Public Sectors. Seminar Public Private Partnerships (PPP) - Global Experience and Challenges in Russia, Feb 10, 2005. Moscow.
  • 4沈际勇,王守清,强茂山.中国BOT/PPP项目的政治风险和主权风险:案例分析..华商·投资与融资.,2005(1)..