文章结合呼和浩特抽水蓄能电站渗漏排水系统的安装与调试,分析了水电站渗漏排水系统(立式深井泵)安装调试的技术特点、介绍了立式深井泵渗漏排水系统的组成、安装调试工艺等。
Based on the installation and debugging of the leakage and drainage system of Hohhot pumped storage power station,the technical features of the installation and commissioning of the leakage and drainage system of the hydropower station(vertical deep well pump)are analyzed,and the composition and installation and commissioning process of the vertical deep well pump leakage and drainage system are introduced.
出处
《电力系统装备》
2018年第9期139-140,共2页
Electric Power System Equipment
关键词
呼蓄
渗漏排水
立式深井泵
安装调试
storage
leakage and drainage
vertical deep well pump
installation and commissioning