直流锅炉制粉系统堵煤的原因分析与改造

Cause Analysis and Transformation of Blocking Coal in Once Through Boiler Pulverizing System
下载PDF
导出
摘要 针对某火力发电厂制粉系统经常堵煤情况,观察分析现场具体的运行情况,发现是给煤机出口煤流中心线与落煤管的中心线不符合。通过加大落煤管尺寸和矫正给煤机煤流中心,以及改造给煤机出口落煤闸板三项改造措施,使系统设计更加合理,解决了制粉系统经常堵煤的问题。 In view of the coal pulverizing system in a thermal power plant,it is found that the coal flow center line of the coal feeder is not consistent with the central line of the coal pipe.By increasing the size of the coal falling pipe and correcting the coal flow center of the coal machine,and the reform of the three reform measures to the coal sluice gate of the coal machine,the system design is more reasonable and the problem of frequent coal plugging in the pulverizing system is solved.
作者 罗汉青 王荦荦 钟振坤 Luo Han-qing;Wang Luo-luo;Zhong Zhen-kun
出处 《电力系统装备》 2018年第8期102-103,共2页 Electric Power System Equipment
关键词 火力发电 制粉系统 堵煤 改造措施 thermal power generation coal pulverizing system coal plugging retrofitting measures
  • 相关文献

参考文献1

二级参考文献7

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部