摘要
随着社会生产力的发展,社会用电需求量呈“喷井式”增长,这对输电线路的建设提出了更高的要求。文中以500kV架空输电线路为例,介绍了张力架线的施工质量控制措施。
With the development of social productivity,the demand for electricity in the society has increased by“spraying well”,which puts forward higher requirements for the construction of transmission lines.The author takes the 500 kV overhead transmission line as an example to talk about the construction quality control measures of the tension line.
出处
《电力系统装备》
2018年第6期70-71,共2页
Electric Power System Equipment
关键词
500KV架空输电线路
张力架线
施工质量控制
500 kV overhead transmission line
tensioned wire
construction quality control