摘要
以"长乐万星电影广场"项目装配式混凝土空心楼盖板施工为背景,阐述地下室顶板结构找坡状况下装配式混凝土空心楼盖板的施工工艺及存在的问题,并提出提高安装精度的措施,从而实现了施工目标,希望对同行有所借鉴。
Based on the construction of assembled concrete hollow floor slab of Changle Wanxing Film Square project, this paper expounds the construction technology and existing problems of the assembled concrete hollow floor slab under the condition of looking for slope of basement roof structure, and puts forward measures to improve the installation accuracy, so as to achieve the construction goal. Hope to draw lessons from colleagues.
作者
陈伟
Chen Wei(Fuzhou No.1 Construction Inc,Fuzhou 350011,China)
出处
《山西建筑》
2019年第4期100-101,共2页
Shanxi Architecture
关键词
空心楼盖板
结构找坡
稳定性
hollow floor structure
structural slope finding
stability