期刊文献+

可变径全圆针梁台车在TBM施工隧洞衬砌中的应用 被引量:2

Application of variable diameter full circle needle beam formwork trolley in tunnel lining of TBM construction
下载PDF
导出
摘要 TBM开挖隧洞,由于刀盘及刀具的限制,目前开挖完的隧洞为同一直径,为了保证后期衬砌施工中结构的强度,需要对不同的围岩类别采取不同的衬砌厚度。研究表明,采取可变径全圆针梁台车进行这方面的衬砌,具有明显的优越性。本文基于吉林引松供水工程项目,论述了可变径全圆针梁台车在TBM施工隧洞衬砌中的应用。 The TBM excavation tunnel,due to the limitation of the boring head and the cutter,the tunnels currently excavated are of the same diameter.In order to ensure the strength of the structure in the later lining construction,it is necessary to adopt different lining thicknesses to different surrounding rock types.Our research indicates that take variable diameter full circle needle beam formwork trolley has obvious advantages in this aspect of lining.Based on the Songhua River water supply project in central Jilin cities,this paper discusses the application of variable diameter full circle needle beam formwork trolley in the TBM construction tunnel lining.
作者 苗双平 徐晨星 韩京华 梅渠舟 马科 MIAO Shuangping;XU Chenxing;HAN Jinghua;MEI Quzhou;MA Ke(Beijing Vibroflotation Engineering Co.,Ltd.,Beijing 100102,China)
出处 《探矿工程(岩土钻掘工程)》 2019年第2期86-90,共5页 Exploration Engineering:Rock & Soil Drilling and Tunneling
关键词 TBM开挖 衬砌 可变径针梁台车 TBM excavation lining variable diameter needle beam formwork trolley
  • 相关文献

参考文献6

二级参考文献3

  • 1刘战辉.北京市南水北调配套工程南干渠工程施工第七标段实施性施工组织设计[R].长春:中铁十三局,2010.
  • 2张琪.南水北调南干渠ZLφ3.4×10.2m全圆针梁台车检算报告[R].北京:北京交通大学,2010.
  • 3贾吉春.南水北调南干渠ZLφ4×10.2m全圆针梁台车技术说明[R].北京:中铁隧道集团二处机械厂,2010.

共引文献20

同被引文献19

引证文献2

相关作者