摘要
结合矿井一采区工况条件制定了五种充填方案,通过对各方案技术特点的比较,综合对回收率、充填工艺和地表变形情况等的分析,最终选用巷道不等强完全充填开采方案。
Five kinds of filling schemes are formulated according to the working conditions of the first mining area in the mine.By comparing the technical characteristics of the schemes and analyzing the recovery rate,filling technology and surface deformation,the unequal-strong fully filling mining scheme is finally selected.
作者
孙志刚
Sun Zhigang(Shuiyu Coal Industry,Fenxi Mining Industry Group Co.,Ltd.,Xiaoyi Shanxi 032300)
出处
《山西冶金》
CAS
2018年第6期143-145,150,共4页
Shanxi Metallurgy
关键词
条带煤柱
矸石充填
方案对比
strip coal pillar
gangue filling
scheme comparison