摘要
文章通过分析天然气发电机组的供电特性以及天然气管道压缩机站的负荷特点,提出安装纯阻性假负载以调节燃气发电机组运行工况的策略。该策略发挥了燃气发电机组的运行特点,能够按照燃气发电机组的最低运行需求来调节机组的实际负荷,从而延长燃气发电机组的大修时限,并使燃气发电机组能够长期平稳的运行。
Through the analysis of the power supply characteristics of natural gas generator set and the load characteristics of gas compressor station,the propose to install the pure impedance dummy load to adjust the gas power generator station is provided.This propose played a running characteristics of the gas generator,also can run according to the minimum gas generator needs to adjust the unit’s actual request,thus increasing the gas generator overhaul time limit,and make the gas generator set running in the long-term smoothly and the best working condition.
作者
李薇
LI Wei(Trans-Tajik Gas Pipeline Co., Ltd.)
出处
《化工管理》
2019年第1期216-217,共2页
Chemical Engineering Management
关键词
假负载
发电机组
管道压缩机站
dummy load
natural gas generator set
compressor station of natural gas pipeline