摘要
本文从优化设计和对降标高段快速安装支架2个方面介绍了红石湾煤矿010801综采工作面在风巷降标高段,实现了支架快速、安全、高效安装的应用实践。
In this paper,from the 2 aspects of optimization design and the rapid installation of the support in the lowering elevation section,the paper introduces the low elevation section of 010801 fully-mechanized mining face in Hongshiwan coal mine,and realizes the application practice of the fast,safe and high-efficiency installation of the support.
作者
蒙鹏科
MENG Pengke(Hongshiwan Coal Mine Limited Liability Shenhua Ningxia Coal Industry Group,Ningxia Coal Industry Group,Yinchuan,Ningxia,750403)
出处
《神华科技》
2018年第12期26-28,32,共4页
Shenhua Science and Technology
关键词
综采工作面
降标高
安装支架
技术研究
Fully mechanized mining face
Lowering elevation
Installation of the support
Technology study