摘要
论文以同煤集团同生树儿里煤业为案例,研究综放工作面过陷落柱的综合技术方案。针对矿压规律研究、采动对陷落柱的活化分析、注浆加固技术、保护煤柱宽度和生产工序优化等关键技术提出了相应的内容和方法,形成了综放工作面过陷落柱的综合技术体系。该研究成果对我国同类型的工作面过陷落柱或其他地质构造具有很好的参考意义。
Taking Shuerli Coal Industry of Tongsheng Coal Group as an example,this paper studies the comprehensive technical scheme of fully mechanized caving face overpassing collapse pillar.Aiming at the key technologies such as the study of strata pressure law,activation analysis of subsidence pillar during mining,grouting reinforcement technology,protection of pillar width and optimization of production process,the corresponding contents and methods are put forward,and a comprehensive technical system for overpassing subsidence pillar in fully mechanized caving face is formed.The research results have a good reference significance for the same type of working face overpassing collapse pillars in China or other geological structures.
作者
岳毅
Yue Yi(Datong Coal Mine Group Tongsheng Shuerli Coal CO.,LTD.,Shanxi,037000)
出处
《当代化工研究》
2019年第2期126-127,共2页
Modern Chemical Research
关键词
综放工作面
陷落柱
综合技术
直接推过
绕过
fully mechanized caving face
collapse column
comprehensive technology
direct push
bypass