伙伴关系下EPC项目联合体风险分担的最优比率分析 被引量:3

Analysis of Optimal Ratio of Risk Sharing of EPC Project Consortium under Partnership
下载PDF
导出
摘要 在伙伴关系的基础上,构建基于博弈理论的设计-采购-施工三方风险分担动态博弈模型,并分析伙伴关系下EPC项目联合体成员的分价值函数。通过建立动态模型并结合纳什协商以及赋值计算可得:伙伴关系下联合体成员共同承担风险所获收益要高于两方或一方承担风险所带来的收益;合理风险比例组合的联合体效益要大于三方平均分担风险所获的效益。 On the basis of the partnership,this paper constructs the dynamic game model of design-procurementconstruction three-party risk sharing based on game theory,and analyzes the sub-value function of the members of EPC project consortium under the partnership.By establishing a dynamic model and combining with Nash negotiation and valuation calculation,concludes that the benefits of the joint risk of the joint members of EPC project consortium under the partnership are higher than the benefits brought by the two parties or one party;the benefits of the reasonable risk ratio combination are greater than the benefits of the tripartite sharing of risks.
作者 王志强 邱倩倩 司曼曼 WANG Zhiqiang;QIU Qianqian;SI Manman(Engineering&Management Institute,Qingdao University of Technology,Qindao 266520,China)
出处 《工程经济》 2019年第2期71-75,共5页 ENGINEERING ECONOMY
关键词 伙伴关系 EPC项目联合体 风险分担 最优比例 partnership EPC project consortium risk sharing optimal ratio
  • 相关文献

参考文献5

二级参考文献55

  • 1赵振宇,刘伊生,乌云娜.建设工程项目Partnering管理方式探究[J].土木工程学报,2005,38(8):123-127. 被引量:21
  • 2唐文哲,强茂山,陆佑楣,陈云华.基于伙伴关系的项目风险管理研究[J].水力发电,2006,32(7):1-4. 被引量:17
  • 3ELLRAM L M. A Managerial Guideline for the Development and Im- plementation of Purchasing Partnerships, International Journal of Pur- chasing and Materials Management, 1991, 27 (3) : 2 -8.
  • 4LANDEROS R, RECK R. Maintaining Buyer - supplier Partner- ships, International Journal of Purchasing and Materials Management, 1995, 31 (3): 3-11.
  • 5MICHAEL J MALONI, W C BENTON. Supply Chain Partnerships: opportunities for operations Research, European Journal of operational Research, 1997, 101:419-429.
  • 6STUART F I. Supplier Partnerships: Influencing Factors and Strategic Benefits, International Journal of Purchasing and Materials Manage- ment, 1993, 29 (4): 22-28.
  • 7SRINAGESH GAVIRNENI. Benefits of co - operation in a production distribution environment, European Journal of Operational Research, 2001, 130:612-622.
  • 8SHANTHIKUMAR J G, SUMITA U. Approximations for the time spent in a dynamic job shop with applications to due date assignment [J]. International Journal of Production Research, 1988, 26: 1329 - 1352.
  • 9KARMARKAR U. Manufacturing lead times, order release and ca- pacity loading [ A ]. In Graves S, Rinnooy Kan A, Zipkin P. (eds.): Handbooks in Operations Research and Management Sci- ence, Vol. 4, Logistics of Production and Inventory [ M ]. Amster- dam: North - Holland, 1993.
  • 10Flyvbjerg B. Over budget, over time, over and over again: Managing major projects [M]// Morris PWG, Pinto J K, Soderlund J. The Oxford handbook of project management. Oxford.. Oxford University Press, 2011: 321-344.