介绍整串落地带电更换220 kV线路双联耐张单片绝缘子的常规作业方法,对作业中需要使用的专用工具以及应注意的安全事项进行说明,根据作业实际情况提出塔上转移整串更换220kV线路双联耐张单片绝缘子的新方法和新工具,新方法的使用与传统作业方法相比较,新方法更加能提高等电位作业的安全性和可靠性。
This paper introduces the routine working method of a series of ground live replacement of 220 kV line double tensioning monolithic insulators,and explains the special tools that need to be used in the operation as well as the safety attention.According to the actual situation of the operation,advane new method and new tool for transferring the whole string of 220 kV line double tension resistant monolithic insulators on the tower,compares.the new operation method with the traditional operation method.The new operation method can improve the safety and reliab ility of the equipotential operation.
作者
刘明亮
李博
卢建树
张健
张超君
LIU Mingliang;LI Bo;LU Jianshu;ZHANG Jian;ZHANG Chaojun(State Grid Hebei Electric Power Co.Ltd.,Hengshui Power Supply Branch,Hengshui 053000,China;State Grid Hebei Electric Power Co.Ltd.,Shijiazhuang 050021,China;State Grid Hebei Electric Power Co.Ltd.,Shijiazhuang Power Supply Branch,Shijiazhuang 050021,China)
出处
《河北电力技术》
2018年第5期48-50,62,共4页
Hebei Electric Power
关键词
带电作业
更换
双联
耐张绝缘子
on-line work
replacement
duplex
tension insulator