期刊文献+

大型抽水蓄能电站基于水淹厂房排水能力的设计分析

Design and Analysis of Large-scale Pumped Storage Power Station Based on Drainage Capacity of Flooded Power Plant
下载PDF
导出
摘要 以大型抽水蓄能电站地下厂房结构为模型,定性分析蓄能水电站供排水系统,介绍了水淹厂房排水能力设计方法以及水淹厂房的事故水源,并提出预防水淹厂房的预防措施及改进建议。 Based on the underground powerhouse structure of large-scale pumped storage power station,qualitative analysis of the water supply and drainage system of the storage power station,the design method of the drainage capacity of the flooded plant and the accident water source of the flooded plant are introduced,and the preventive measures for preventing the flooding plant are proposed. Suggestions for Improvement.
作者 李开明 廖中友 Li Kai-ming;Liao Zhong-you
出处 《电力系统装备》 2019年第4期213-214,共2页 Electric Power System Equipment
关键词 水电厂 水淹厂房 排水计算 事故水源 应急处置 hydropower plant flooded plant drainage calculation accident water source emergency treatment