摘要
在铁路工程建设中,路基处理是关系到铁路使用质量的重要因素之一。由于铁路跨度较大,会经过多种复杂的地质条件,因地制宜地进行路基的加固处理就显得十分必要。结合某铁路工程实例,分别介绍了碎石桩法、静力排水固结法和换填法3种路基施工方案,并从多个角度对这3种方案进行了对比,从中选择的一种最优方法,针对施工中的技术控制措施展开了分析。
In the construction of railway engineering,roadbed treatment is one of the important factors related to the quality of railway use.Due to the large span of the railway,it will be necessary to carry out a variety of complex geological conditions,and it is necessary to carry out the reinforcement of the roadbed according to local conditions.Combined with a railway engineering example,the three roadbed construction schemes of gravel pile method,static drainage consolidation method and replacement method are introduced respectively,and these three schemes are compared from various angles.The best method,and finally the analysis of the technical control measures in the construction.
出处
《建筑技术开发》
2019年第1期58-59,共2页
Building Technology Development
关键词
铁路工程
路基施工
碎石桩法
换填法
控制措施
railway engineering
subgrade construction
gravel pile method
replacement method
control measures