摘要
地下工程施工时,穿越高地温区域时,会对整个隧道的施工安全及工期影响巨大。文章针对桑珠岭隧道高地温实际情况,通过高地温成因进行分析,制定了详细的设计方案,并确定了施工流程,以确保隧道施工的顺利进行。
During the construction of underground engineering,when crossing the high ground temperature area,it will have a tremendous impact on the construction safety and duration of the whole tunnel.According to the actual situation of high ground temperature in Sangzhuling Tunnel,through the analysis of the causes of high ground temperature,this paper formulated a detailed design scheme and determines the construction process to ensure the smooth progress of tunnel construction.
作者
吴彪
WU Biao(The First Engineering Co.,Ltd.,China Railway No.5 Group,Changsha,Hunan 410117,China)
出处
《企业技术开发》
2019年第2期36-39,共4页
Technological Development of Enterprise
关键词
隧道
高地温
超前预判
施工流程
施工措施
Tunnel
High ground temperature
Anticipation
Construction process
Construction measure